The obligation to complain

29 July 2024

The obligation to complain

By Zoë Ris

It often occurs that an object does not correspond to what has been agreed. After the delivery of a property, for example, hidden defects may arise.

In such cases, it is important that you raise the issue in a timely manner. If you fail to complain in time, you forfeit the right to hold the other party accountable. In other words, you end up empty-handed if you complain too late. But what is considered timely and what is considered late?

Background

The obligation to complain can be found in Articles 6:89 and 7:23 of the Dutch Civil Code. The purpose of these provisions is to protect the debtor against belated and difficult-to-verify complaints. According to these articles, the debtor may assume that the creditor promptly investigates whether the performance complies with the agreement. Consider, for example, the purchase of a house. If the house has defects, the seller may assume that the buyer promptly informs the seller about this so that the seller has the opportunity to defend himself.

Commencement of the time limit for lodging a complaint

The time limit for lodging a complaint starts running from the moment the buyer has discovered or should have discovered the defect. In case of a consumer purchase, the consumer has timely complained if he does so within 2 months. If it is not a consumer purchase, it cannot be definitively stated when a complaint is considered timely. The law does not provide a specific deadline.

To determine whether a complaint is timely, all relevant circumstances must be taken into account according to the Dutch Supreme Court. In particular, the potential disadvantage caused to the debtor by the delayed complaint is relevant, but also the expertise of the parties and the visibility of the deviation play a role, for example.

An example: Complaint made 12 years after purchasing a house

In 2007, a buyer purchased an apartment from a seller. In the years following 2007, the buyer experienced several leakages. These were temporarily fixed with sealant, but the periods between leakages became shorter. Ultimately, in 2019, the buyer instructed an expert to investigate the situation. The seller was informed about this. The expert concluded that the leakages were caused by defects in the construction of the apartment. The buyer then requested the seller to rectify the defects at his expense. The seller refused, leading to legal proceedings.

District Court

According to the District Court, the buyer complained too late, as the seriousness of the defects gave cause for an earlier complaint. Additionally, the District Court ruled that the seller was disadvantaged in his defence and recourse options due to the long delay. Therefore, the buyer’s claims were dismissed.

Court of Appeal

The buyer did not accept this decision and appealed. The Court of Appeal ‘s-Hertogenbosch ruled differently. According to the court, there was no breach of the obligation to complain because in 2019, as soon as there was reason to doubt the construction’s integrity, the buyer had an investigation conducted and informed the seller. Only after this investigation did the buyer become aware of the serious structural defects. The complaint period started running from that moment according to the court. Furthermore, the court ruled that the seller was not disadvantaged in his defence and recourse options.

Conclusion

Although the outcome was favourable for the buyer in this case, failing to complain (timely) can have significant consequences. There had already been multiple instances of leakage, raising questions about whether it could have been expected of the buyer to conduct an earlier investigation into the cause of the leakage. In other words, the outcome could have been different.

More information

Are you facing defects or being held accountable for them? Feel free to contact us to discuss your options.

Related blogs

Previous slide
Next slide

26 March 2026

The conditions for a bank guarantee to lift a seizure

Provisinal (or prejudgment) seizure of a bank account is a powerful tool for creditors to safeguard their recourse position, before a court has ruled definitively on a claim. For the party whose assets are attached, however, such attachment can be highly disruptive.

Read more

Read more about

19 February 2026

The effect of a conversion notice in contracts for works

Suppose a contractor has been engaged under a contract for works, but a problem arises during the execution of those works. Unfortunately, this happens quite often. If the parties are unable to resolve the issue together, it is advisable to consider legal steps. Below is a practical explanation and five useful tips.

Read more

Read more about

29 January 2026

Another brick in the wall

Are you planning to build or renovate? If so, a number of questions arise straight away: which type of agreement for contracting works is best for you? Do you opt for a fixed contract price, a target price, or a contract based on hours worked? Are any general terms and conditions applicable and, if so, which ones? Below is a practical guideline.

Read more

Read more about

8 January 2026

Rent and valuation fictions in the WOZ Act: how does it actually work?

The WOZ value of a property is its estimated market value. In other words, it is the price that would be paid by the highest bidder if the property were sold in the best possible way. Each year, the municipality determines this value and assigns it to a property on the basis of sale prices of comparable properties in the area.

Read more

Read more about

17 December 2025

The penalty clause in a property purchase agreement

Buying a home is not something most people do every day. It is therefore important that both parties understand the obligations arising from a property purchase agreement.

Read more

Read more about
All articles