15 February 2023

Salvaging a carelessly prepared permit under the Environment and Planning Act

By Marie-Christine Veltkamp-van Paassen

What is careful preparation?

Article 3:2 of the General Administrative Law Act (Algemene wet bestuursrecht, Awb) requires an administrative body to gather the necessary knowledge about the relevant facts and interests to be weighed when preparing a decision. Only then can the municipality reach a careful decision. The municipality is required to consider not only its own interests or those of the property developer, but also those of other parties concerned, such as local residents. That this requirement is not to be taken lightly was demonstrated by a very recent ruling by the Administrative Law Division of the Council of State. Is there any recourse for the municipality and property developer in the case of a flawed decision? In this blog, we will discuss everything about salvaging a carelessly prepared environmental permit.

Case study of the zoning plan for the HBG site in Rijswijk (ZH)

On 21 April 2021, the Division ruled[1] in a case brought by a person concerned opposing the adoption of the zoning plan ‘redevelopment HBG site’ by the municipality of Rijswijk (ZH). Among other things, the plan allows for the construction of 550 housing units, divided into five residential towers, plus a few town houses. The person concerned lives on a parcel adjacent to the plan area. He disagrees with the plan because of the impact it will have on his residential and living environment.

The person concerned had pulled out all the stops in the hope that the decision to adopt the plan would be overturned. He raised as many as 11 different grounds against the decision: His parcel was wrongly not included in the plan; it was wrongly ruled that an environmental impact report did not have to be drawn up; there was a violation of the South Holland Environment Ordinance; his privacy and views had not been taken into account; the adoption of the plan was contrary to a letter previously sent by the Municipal Executive; the loss of green space was unacceptable; protected birds lived in the plan area; traffic nuisance could be anticipated; there was also insufficient parking space; there was an anticipated increase in noise nuisance due to increased traffic movements; and air pollution would increase.

Annulment of the decision adopted

The Division concluded after ample consideration that the arguments presented by this person concerned failed on almost all grounds. However, on the last two grounds, the Division agreed with the person concerned in accordance with Article 3:2 of the General Administrative Law Act. Indeed, the documents showed that the municipality had not taken into account noise levels at the home of the person concerned when adopting the zoning plan. While there was a noise report, this report was dated after the date of adoption of the decision. Furthermore, there was no evidence that the municipality had sufficiently taken into account the impact on air quality at the home of the person concerned when adopting this decision. While there was an air quality report, it was flawed because it incorrectly deducted 920 car movements for an office building that had been vacant for some time.

Article 8:72(1) of the General Administrative Law Act provides that a decision must be set aside, in whole or in part, if it is determined that it was reached  without sufficiently careful preparation. The Division did just that; it annulled the decision to adopt the zoning plan. It goes without saying that this, in principle, has far-reaching implications for both the municipality and the project developer concerned.

Salvaging a flawed decision

However, in this particular case, in terms of noise levels, the — albeit late — noise assessment showed that at the site of the home of the person concerned, the impact of the plan on noise levels was negligible. On the issue of air quality, the municipality had commissioned a remedial report pending the proceedings. It followed that even taking into account the 920 traffic movements previously wrongly deducted, it could not be concluded that air quality would be compromised by the plan. For these reasons, the Division determined that the legal effects of the decision adopted would remain in place. The Division was entitled to do so under Article 8:72(3a) of the General Administrative Law Act. As a result, the plans of the municipality and the project developer were salvaged after all.

The conclusion?

The development of habitats has many facets, and all these facets must be thoroughly addressed in the preparation. Given the above ruling, the municipality cannot, in principle, afford to make a mistake in this regard. This is in the interest of the municipality which is keen to make progress in developing habitats. However, it is also in the interest of the project developer who wanted to realise its plans. If an omission in the decision-making process does occur, it is important to act appropriately. One must also ensure that the legal consequences of the decision are upheld.

Would you like more information?

Do you have any questions about salvaging a carelessly prepared permit? If you would like advice or have another legal question, please do not hesitate to contact me.

[1] ECLI:NL:RVS:2021:855

 

Related blogs

Previous slide
Next slide

26 March 2026

The conditions for a bank guarantee to lift a seizure

Provisinal (or prejudgment) seizure of a bank account is a powerful tool for creditors to safeguard their recourse position, before a court has ruled definitively on a claim. For the party whose assets are attached, however, such attachment can be highly disruptive.

Read more

Read more about

19 February 2026

The effect of a conversion notice in contracts for works

Suppose a contractor has been engaged under a contract for works, but a problem arises during the execution of those works. Unfortunately, this happens quite often. If the parties are unable to resolve the issue together, it is advisable to consider legal steps. Below is a practical explanation and five useful tips.

Read more

Read more about

29 January 2026

Another brick in the wall

Are you planning to build or renovate? If so, a number of questions arise straight away: which type of agreement for contracting works is best for you? Do you opt for a fixed contract price, a target price, or a contract based on hours worked? Are any general terms and conditions applicable and, if so, which ones? Below is a practical guideline.

Read more

Read more about

8 January 2026

Rent and valuation fictions in the WOZ Act: how does it actually work?

The WOZ value of a property is its estimated market value. In other words, it is the price that would be paid by the highest bidder if the property were sold in the best possible way. Each year, the municipality determines this value and assigns it to a property on the basis of sale prices of comparable properties in the area.

Read more

Read more about

17 December 2025

The penalty clause in a property purchase agreement

Buying a home is not something most people do every day. It is therefore important that both parties understand the obligations arising from a property purchase agreement.

Read more

Read more about
All articles